TEMPORARY FACILITIES

Imagen1.jpg
Imagen2.jpg

SITE OPTION 1

1.jpeg

SITE OPTION 2

PROGRESS OF THE SITES ACTUAL PROJECT CONSTRUCTION

Site Option 1: Rio Alejandro Energy Park
✅ Enviromental Permit obtained

✅ Construction Permits obtained

✅ Temporary access road finished and final access road ongoing

✅ Site levelling works for both the Power Block and the Regasification Plant (Onshore part of the LNG Terminal) finished.

✅All preparation works are being carried out to start foundations in order to be ready before the equipment arrives at site.

✅ Temporary facilities are finished

Site Option 2: Isla Margarita
✅ Sea-bed Concession obtained and sub-lease Concession obtained;
✅ Pier construction in progress

STRATEGIC ALLIANCES

AREA FOR THE DEVELOPMENT OF
THE SINOLAM LNG PROJECT

Imagen3.png
2.jpeg

VEGETATION REMOVAL
DEFORESTATION AT 43.4 Ha

Imagen4.jpg
Imagen5.jpg

TEMPORAL ACCESS ROAD 4KM

Imagen6.jpg
Imagen8.jpg

SITE LEVELLING

Imagen9.jpg
Imagen10.jpg

TOTAL OF EXCAVATED & BACKFILLED MATERIAL = 900,000 M3 (x 2)  1,800,000 M3

AUGUST. 2018

Imagen14.jpg

NOW

Imagen13.jpg

TEMPORARY FACILITIES