TEMPORARY FACILITIES


SITE OPTION 1

SITE OPTION 2
PROGRESS OF THE SITES ACTUAL PROJECT CONSTRUCTION
Site Option 1: Rio Alejandro Energy Park
✅ Enviromental Permit obtained
✅ Construction Permits obtained
✅ Temporary access road finished and final access road ongoing
✅ Site levelling works for both the Power Block and the Regasification Plant (Onshore part of the LNG Terminal) finished.
✅All preparation works are being carried out to start foundations in order to be ready before the equipment arrives at site.
✅ Temporary facilities are finished
Site Option 2: Isla Margarita
✅ Sea-bed Concession obtained and sub-lease Concession obtained;
✅ Pier construction in progress
STRATEGIC ALLIANCES
AREA FOR THE DEVELOPMENT OF
THE SINOLAM LNG PROJECT


VEGETATION REMOVAL
DEFORESTATION AT 43.4 Ha


TEMPORAL ACCESS ROAD 4KM


SITE LEVELLING


TOTAL OF EXCAVATED & BACKFILLED MATERIAL = 900,000 M3 (x 2) 1,800,000 M3
AUGUST. 2018

NOW

TEMPORARY FACILITIES